Whitby’s Ordsall Chord challenge fails

15 Oct 15 An attempt by former Institution of Civil Engineers president Mark Whitby to block an £85m railway scheme in Manchester has failed.

Network Rail plans to build a 340-metre stretch of rail called the Ordsall Chord to link Manchester’s three main railway stations – Piccadilly, Victoria and Oxford Road – to improve rail capacity and create new routes.

It will link the Bolton and Chat Moss lines, with a new bridge over the River Irwell and a viaduct over Trinity Way.

Mark Whitby argued that the scheme would damage railway heritage and prevent old trains getting to the 185-year-old Grade I listed Liverpool Road Station, which is part of Manchester’s Museum of Science & Industry. His legal challenge has now been thrown out.

Network Rail was happy to see the judge dismiss the challenge. A Network Rail spokesman said: “We welcome this decision as the Ordsall Chord forms a key part of our railway upgrade plan for the north of England. More than £1bn is being invested to provide passengers with better services and we plan to start work on the Ordsall Chord as soon as possible.�

The judgment was handed down by Mrs Justice Lang in the Planning Court in London.  She dismissed all three claims made by Mark Whitby: two statutory challenges of the Transport & Works Act order, one of the Listed Building Consent and a judicial review of the planning permission.  Mrs Justice Lang also refused permission for Mr Whitby to appeal.